Design-Build in Practice (II): What nobody will see later on

For around two months now, work on the new Curana Medizin AG Permanence practice at the Haus zum Falken near Zurich Stadelhofen railway station has been in full swing.

Following several practice projects we have carried out together, we are once again working closely with our client, Michael Messerli, on this extension. Direct communication and short decision-making processes enable requests and adjustments to be incorporated immediately into the ongoing construction work. The fact that planning, coordination and implementation are closely interlinked at Integral pays particular dividends at this stage: issues can be clarified straight away and decisions integrated directly into the ongoing work without delay. 

Following the initial structural alterations and basic installations, September was entirely devoted to the technical fit-out phase. Much of the work carried out over the past few weeks will be barely visible, if at all, in the finished space. Yet it is precisely this work that forms the foundation for the quality, functionality and operational safety of the future practice. 

The ceiling as a coordination zone

Much of the work over the past few weeks has taken place on the ceilings. Mega Bau AG carried out the finishing plasterwork, thereby laying the foundations for the next stages of the fit-out. At the same time, Meier Kopp Services AG insulated the cooling pipes with rubber, Isolag AG erected the substructures for the suspended ceilings, and preparations were made for the subsequent lighting installations. Even at this stage, building services, lighting and the fit-out must be precisely co-ordinated to ensure that everything fits together later on.

The technical infrastructure is expanding

The electrical infrastructure also began to take shape in September. The new sub-distribution board was installed by EZ Elektro AG, the cabling work was in full swing, and the UKV cables for the communications infrastructure were laid. At the same time, the infrastructure for the central rack was being installed. 

It is precisely during this phase of construction that the complexity of modern interior fit-outs becomes apparent: electrical, communications, HVAC and finishing works all share the same installation spaces and must be precisely coordinated in terms of both space and scheduling.

Technical equipment under the raised floor

Another important part of the building services is located in the cavity beneath the raised floor, which will not be visible once the work is complete.

Here, pipes were routed, technical components were installed and, amongst other things, the change-over system for heating and cooling was fitted. Before the raised floor panels could be laid, the cavities were cleaned and all installations were checked once again.

This was followed by a 24-hour pressure test on the pipework. Only after the system had been successfully tested for leaks could the raised floor panels be fitted and the installations permanently sealed. 

Integral-Stadelhofen-12903.jpg

Quality that remains hidden later on

In parallel with the technical installations, the necessary fire and sound barriers were installed. Cable penetrations and installation areas were professionally sealed in accordance with the requirements.

This work will later be completely concealed behind ceilings, walls or floor structures. However, it is of central importance for the safety, comfort and long-term reliable operation of the practice. 

Design-build streamlines the process

It is precisely during this phase of construction that the added value of the design-build model becomes particularly evident. The various trades must not only function independently, but must also be coordinated with one another in terms of space, technical requirements and timings.

As planning, coordination and implementation are closely interlinked at Integral, decisions can be made at an early stage and any issues can be clarified directly with the contractors. This reduces the need for coordination, increases planning certainty and ensures construction progresses smoothly.

With the completion of the technical fit-out phase, the initial concepts are now becoming increasingly visible. The final interior fit-out is already in full swing. Joinery work, lighting installations and painting now characterise the scene on the building site.

--